Geotechnical Engineering Projects

Performance for the Completed Geotechnical Engineering Work to-date: July 2012

NO.

PROJECT TITLE

SCOPE OF WORKS

CLIENT/ INSTALLER

Description of the project/ Performance

1.

KERJA-KERJA MEMBAIKI CERUN YANG RUNTUH DI KAWASAN JALAN KUALA MENTIGA - TERAPAI, PEKAN, PAHANG

Year: 2008

SLOPE REPAIR WORK

  1. GEOGRID Wall
  2. Total Height: 25 m
  3. TRM ECOMAX

JKR KUANTAN/ MTS FIBROMAT SDN BHD

The site is located at KM31, Luluan C108, Jalan Kuala Mentiga-Terapai, Pekan, Pahang. Slope failure at the aforesaid location is due to excessive rainfall whereby occurring high flow of surface water runoff induced water seeping into the slope.Thus, an appropriate slope reinforcement, erosion protection and long term vegetation growth need to be introduced to customize the more cost effective solution for our client site – on specification, up to code, within budget and permanent problem solving for this two location of about 500 m length.Currently, the Reinforced Earth Wall is in good condition.

2.

FACTORY CONSTRUCTION IN RAWANG

Year: 2008

SLOPE EROSION CONTROL

  1. TRM ECOMAX
  2. GEOGRID
  3. Total Height 12m

EVERSENDAI CORPORATION/ BARISAN PERFORMA SDN BHD

The factory and office development located at Lot 472, Mukim Rawang, Selangor. 12 m geogrid wall was used to form a boundary retaining wall with total length of 524 m.

Hacent Consultant was the independent checker for the stability of the wall after some crack lines observed. Remedial works had been proposed and currently, the Reinforced Earth Wall is in-tact.

3.

EARTH RETAINING WALL SYSTEM AT ZOO VIEW DEVELOPMENT

Year: 2009

REINFORCED EARTH WALL

  1. GEOGRID (8m + 4 berms)
  2. Total Height: 12 m
  3. HIGH STRENGTH GEOTEXTILE

ASSET 1 AUS (ULU KLANG) S/B/ Impex Bio-engineering Sdn Bhd

The site is located at Lot 776 & 682, Mukim Hulu Klang, Daerah Gombak, Selangor. 8 m height Geogrid Wall with 4 m additional slope berm (Total different height: 12m) had been built and act as the boundary wall.
The length of wall is about 250 m with 8 m wall + 4 m berm and 8 m height wall only.

Currently, the Reinforced Earth Wall is in good condition.

4.

IRAQ EMBASSY PUTRAJAYA PRECINCT 15

Year: 2009

REINFORCED MODULAR BLOCK WALL

  1. GEOGRID
  2. Total Height 25m

IRAQ EMBASSY/
SEROJA YAKIN (M) S/B/ Impex Bio-engineering (M) Sdn Bhd

Proposed Iraq embassy resident had been constructed at Precinct 15, Putrajaya. The modular block with geogrid had been built to form the platform as access road and berm drain.

The length of wall is more than   1 km with wall height of 3 to 5 m. The total different height is about 25 m.

Currently, the Reinforced Earth Wall is in good condition.

 

5.

DAMAI PERDANA, CHERAS

Year: 2010

REINFORCED MODULAR BLOCK WALL

  1. GEOGRID (9m)

KEJURUTERAAN MAHAJAYA/ Landasan Impian Sdn Bhd

Proposed residential development at Lot 1073, Damai Perdana, Cheras. The modular block with geogrid was built up to 9 m height.

The length of wall is about 300 m and the wall act as the boundary wall between the existing housing estate and the proposed development.

Currently, the Reinforced Earth Wall is in good condition.

 

6.

SAUJANA IMPIAN, KAJANG

Year: 2010

REINFORCED MODULAR BLOCK WALL

  1. GEOGRID (7.3 m) + 6 m height berm.
  2. Total Height: 13.3 m.

BANDAR SUBANG SDN BHD
(FARLIM GROUP)/ Landasan Impian Sdn Bhd

The site is located at Saujana Impian, Kajang Section 9, Daerah Ulu Langat, Selangor. A modular block wall system (height vary from 4.1m to 7.3m) and 6 m height slope berm at behind the wall.

The length of wall is about 150 m and the wall act as the boundary wall adjacent to the access road.

Currently, the Reinforced Earth Wall is in good condition.

7.

SEKOLAH MENENGAH KEBANGSAAN PRESINT 5(1), PUTRAJAYA (48 BD)

Year: 2010

REINFORCED MODULAR BLOCK WALL

  1. GEOGRID (9m)


EARTHWORK

PEMBINAAN JAYA ZIRA SDN BHD/ Landasan Impian Sdn Bhd

The proposed school development located at Precinct 5, Putrajaya.
9 m height of modular wall had been built as the boundary wall.
The length of wall is about 500 m.

Currently, the Reinforced Earth Wall is in good condition.

 

 

8.

PROPOSED MODULAR BLOCK WALL AT JALAN BESELAH, KUANTAN

Year: 2010

REINFORCED MODULAR BLOCK WALL

  1. GEOGRID (7m)


EARTHWORK

LANDASAN KAPITAL S/B/
JABATAN PERTAHANAN MALAYSIA/ Landasan Impian Sdn Bhd

The proposed Jabatan Pertahanan Malaysia Development located at the Jalan Berselah, Kuantan.

The modular wall with geogrid was used to form the platform of the development and the wall length is about 300 m.

Currently, the Reinforced Earth Wall is in good condition.

 

9.

CADANGAN PEMBANGUNAN SEMULA DI KEM PASUKAN GERAKAN AM (PGA) BATALION 5 DI ATAS LOT 3122, MUKIM SIMPANG RENGGAM, JOHOR (PAKEJ 3)
Year: 2010

REINFORCED MODULAR BLOCK WALL

  1. GEOGRID (12 m & 5m)


EARTHWORK

ISYODA SDN BHD/ Landasan Impian Sdn Bhd

The project located at the Simpang Renggam, which is hilly site formation. Therefore, Reinforced Earth Wall with modular block was used to form the platform.

There are three (3) wall location, with 5 m, 6 m with berm of 3 to 6 m for 200 m length.

Currently, the Reinforced Earth Wall is in good condition.

 

HP CAMPUS, CYBERJAYA

Year:2010

REINFORCED MODULAR BLOCK WALL

  1. GEOGRID (7m)


EARTHWORK

CYBERVIEW SDN. BHD./ Impex Bio-Engineering (M) Sdn Bhd

The project located at Cyberjaya as the HP Campus. The wall was built to form the access road and modular block and geogrid was used.

The wall length is about 150 m and currently, the Reinforced Earth Wall is in good condition.

 

11.

SG PERAK R&R

Year: 2010

REINFORCED MODULAR BLOCK WALL

  1. GEOGRID (5m)


EARTHWORK

JPS, PERAK/ Impex Bio-Engineering (M) Sdn Bhd

The Modular Block wall with geogrid was used to form the platform of the Sg Perak R & R extension works development.

The length of wall only 50 m and currently, the Reinforced Earth Wall is in good condition.

12.

TAMAN NUSA IDAMAN SLOPE REHABILITATION WORK (FASA 7)
FASA 7 PTD 168904 - PTD 169257
MUKIM PULAI, DAERAH JOHOR BAHRU

Year:2011

REINFORCED MODULAR BLOCK WALL

  1. GEOGRID (4m)+ Berm 8 m
  2. Total height: 12 m

EARTHWORK
ROCK HACKING
GEOCELL

NUSAJAYA DEVELOPMENT S/B/ MTS Construction (M) Sdn Bhd

The strengthening Work for the existing slope had been proposed by using modular wall with geogrid. The total different height of the slope is 12 m.

The total length is the wall is about 2 km and currently, the Reinforced Earth Wall is in good condition.

13.

MIX DEVELOPMENT AT TANAH KERAJAAN, MUKIM GALI, RAUB

Phase 1 – Geosynthetic wall 20m high
Phase 2 – Geosynthetic wall 6m high
Phase 3 – Geosynthetic wall 12m high

Year: 2011

REINFORCED GEOGRID WALL

SOIL STABILIZATION WORK

EROSION CONTROL WORK

EARTHWORK

 

 

PERBADANAN SETIAUSAHA KERAJAAN PAHANG/
TERATAI KILAUAN S/B/
Landasan Impian Sdn Bhd

The proposed mixed development project located at the Raub Town next to the court house. The project located at the hilly formation. Thus, major geotechnical works had been constructed such as soil nails, guniting wall, geogrid wall, reinforced earth wall and etc.

Thrree (3) Reinforced Earth Wall location consists of 6 m, 12 m and 20 m had been built and act as the boundary wall.

The length of 6 m wall is about 250 m, 12 m wall of 254 m and 20 m wall of 152 m.

Currently, the Reinforced Earth Wall is in good condition.

14.

SHORELINE PROTECTION WORK FOR MIX DEVELOPMENT AT SUNGAI KARANG, KUANTAN

Year: 2011

REINFORCED GEOGRID  WALL  & MODULAR BLOCK WALL SYSTEM (5m)

SOIL STABILIZATION WORK
& EARTHWORK

EROSION CONTROL WORK

SANUBARI SEJAHTERA S/B
(PJ DEVELOPMENT GROUP)/ Impex Bio-Engineering (M) Sdn Bhd

The costal line protection works had been proposed for the mixed development next to Swiss Graden Resort, Sungai Karang, Kuantan.

5 m height of modular wall had been built in order to create platform at the development and act as the boundary wall and shore line protection system.

The wall is about 200 m and currently, the Reinforced Earth Wall is in good condition.

15.

MIX DEVELOPMENT AT TANAH KERAJAAN, PANDAMARAN, KLANG (FASA 1A9ii)b
Year: 2011

REINFORCED GEOGRID WALL SYSTEM (5m)
SOFT GROUND TREATMENT
RIVER EROSION PROTECTION

LIK TIN CENTURY S/B/
PKNS/ Impex Bio-Engineering (M) Sdn Bhd

The proposed Reinfored Earth Wall is proposed to form a platform and all the wall was sit on bakau pile as the soft  ground site.

The wall is about 150 m and currently, the Reinforced Earth Wall is in good condition.

16.

Land Fill at Ulu Turang, Pahang

Year: 2011

REINFORCED EARTH WALL

  1. GEOGRID (12m + 12 berms)
  2. Total Height: 24 m

HIGH STRENGTH GEOTEXTILE
FOUNDATION: GROUND REPLACEMENT

CYPARK Berhd/ YCN Construction Sdn bhd

Proposed geogrid wall with high strength geotectile was used to form a platform of the land fill area at Ulu Turang, Pahang.

The Reinfored Wall consists of 12 m (Geogrid Wall) + 12 m (berm) and 12 m height geogrid wall only. The length of wall is about 500 m and wall is under construction.

17.

PROPOSED RE WALL - PROPOSED
LUBOK ANTU / LEMANAK / ENGKARI ROAD
(PHASE III - FROM NG. KESIT TO NG. GUGU)
Year: 2010

REINFORCED EARTH WALL

  1. Steel Strip
  2. High Geotextile
  3. 12 m height

Hock Seng Lee Bhd/ GW Builder Sdn Bhd

12 m Reinfored Earth Wall had been proposed and built at the proposed Lubok Antu/ Lemanak/ Engkari Road and act as the road side vertical structures to form the platform level.

The length of the wall is about 125 m and currently the wall is in good condition.

18.

PROPOSED LRT CONSTRUCTION AND COMPLETION OF FACILITIES WORKS FOR AMPANG LINE EXTENSION PROJECT
Year; 2011

REINFORCED EARTH WALL

  1. Steel Strip
  2. High Geotextile

12- 15  m height

Lm Partners Sdn Bhd/ GW Builders Sdn Bhd

12 m to 15 m height of RE Wall had been proposed to form the railway track platform along the Ampang line.

The length of the wall is about 150 m and currently the wall is under construction.

19.

Proposed Housing Development On Bermilik
(Plot G) Jalan Ipoh Bandar Baru Selayang Daerah
Gombak Selangor Darul Ehsan For Wirama Sdn
Bhd.
Year: 2007

REINFORCED EARTH WALL

  1. Steel Strip
  2. High Geotextile

9- 13  m height,
6 m height

Wirama Sdn Bhd/ GW Engineering Sdn Bhd

Few  Reinfored Earth Walls, i.e. 9 to 13 m & 6 m, respectively,  had been proposed and built at the proposed mixed residential development of Plot G, Jalan Ipoh, Selayang as the vertical structures to form the platform level.

The length of the wall is about 300 m and 65 m, respectively and currently the wall is in good condition.

20.

Kerja-kerja Penambahan Tempat Letak Kereta
Terbuka Di Parcel C Presint 1 Pusat Pentadbiran
Kerajaan Persekutuan.
Year: 2007

REINFORCED EARTH WALL

  1. Steel Strip
  2. Ground Anchor

6 m height

Cara Ikram Sdn bhd/ Gw Engineering Sdn Bhd

Reinfored Earth Wall had been proposed and built along the car park boundary to form the platform.

The length of wall is about 200 m and currently the wall is in good condition.

21.

Cadangan Pembangunan Usahasama Di Antara
Majlis Perbandaran Subang Jaya Dan Tetuan
Nurani Gemilang Sdn Bhd Yang Mengandungi 36
Unit Kedai Pejabat 3 Tingkat Dan 1 Unit
Pencawang Elektrik TNB Di Atas Lot 2767, 549,
550 & 551 Batu 11 Puchong Daerah Petaling
Selangor Darul Ehsan.
Year; 2007

REINFORCED EARTH WALL

  1. Steel Strip
  2. Ground Replacement with Crusher run.

6 - 12 m height

Crescendo Infra Sdn Bhd/ GW Engineering Sdn Bhd

Few  Reinfored Earth Walls, i.e. 9 to 12 m & 6 m, respectively,  had been proposed and built at the proposed commercial development along the Jalan Puchong as the vertical structures to form the platform level.

The length of the wall is about 250 m and currently the wall is in good condition.

22.

Cadangan Pembangunan Kediaman Pangsapuri
Di Atas Lot 1310, 1353-1359, 1362-1366 Puchong
Jaya, Daerah Petaling, Selangor For Trientel
Industries Sdn Bhd
Year: 2008

REINFORCED EARTH WALL

  1. Steel Strip
  2. High Geotextile
  3. Ground Replacement

6- 12  m height,
Total Height: 25m

GW Engineering Sdn Bhd

The high wall and berm slope had been built by using RE Wall and Slope in order to create platform for the building works.

Two walls had been constructed, i.e. 12 m RE Wall with 12 m berm, and 6 to 9 m with 6 to 9 m berm, respectively.

The length of wall is about 200 m and 100 m, respectively.

Currently, the Reinforced Earth Wall is in good condition.

23.

Pembinaan Kompleks Ibu Pejabat Lembaga
Pertubuhan Peladang (LPP) Malaysia, Kuala Lumpur
Year: 2009

REINFORCED EARTH WALL

  1. Steel Strip

6 - 9 m height

Panzana Enterprise Sdn Bhd/ GW Engineering Sdn bhd

Reinfored Earth Wall had been proposed and built along the building boundary  to form the platform.

The length of wall is about 100 m and currently the wall is in good condition.

24.

Cadangan Mendirikan 54 Yunit Rumah
Berkembar 3 Tingkat Diatas Lot Pt 32431-32476
Dan PT 32480-32485 Seksyen 1 Kota
Damansara Petaling Jaya Selangor Darul Ehsan
For Tetuan Tropicana Indah Sdn Bhd
Year: 2010

REINFORCED EARTH WALL

  1. Steel Strip
  2. High Strength Geotextile

6 - 9 m height + 6 m barm;
Total Height: 12- 15 m

Panflex Sdn Bhd/ GW Engineering Sdn bhd

Reinfored Earth Wall had been proposed and built along the Lot boundary  to form the platform of access road.

The length of wall is about 300 m and currently the wall is in good condition.

25.

Project: Cadangan Pembangunan Kinrara Estate
Diatas Lot 3197, 3198 & 1804 Mukim Petalling, Daerah Petaling, Selangor
Year: 2010

REINFORCED EARTH WALL

  1. Steel Strip
  2. High Strength Geotextile

6 - 9 m height + 6 m barm;
Total Height: 6- 9 m

 

6 -9 m Reinfored Earth Wall had been proposed and built at the proposed access Road along the housing development as the vertical structures to form the platform level.

The length of the wall is about 500 m and currently the wall is in good condition.

GEOTECHNICAL PROJECTS (SELECTED ONLY)

No

CONTRACT/PROJECT AND SCOPE OF WORKS

COST (RM)

START DATE

COMPLETION DATE

CLIENT

1

PROPOSED SOIL NAILS & GUNITING WALL AT P.T.24380,
KAWASAN PERINDUSTRIAN UTAMA, NILAI 3, NEGERI
SEMBILAN

2M

2007

2007

MEGASOIL ENGINEERING S/B

2

PROPOSED EARTHWORK AND INFRASTRUCTURAL
WORKS FOR 11 MILES, JALAN PUCHONG, PETALING
DISTRICT, PUCHONG ROAD, SELANGOR

2M

2004

2007

NURAINI GEMILANG SDN BHD

3

FAILURE INSPECTION REPORT & REMEDIAL PROPOSAL
FOR THE FAILUE CRIB WALL AT BENTONG SCHOOL,
PAHANG

5M

2007

2008

ARAHECTER S/B

4

PROPOSED COMMERCIAL HIGH VALUE TEMPERATE
HORTICULTURAL CROP ATTANAH RATA, CAMERON
HIGHLAND, PAHANG DARUL MAKMUR

6M

2008

2009

WEST TEC S/B

5

CADANGAN MEMBINA INSTITUT KEMAHIRAN BELIA
NEGARA (IKBN), KUALA LANGAT SECARA RUNDINGAN
TERUS/ REKA & BINA.

20M

2007

2009

JURUTERA KONSULT MAJU S/B

6

PROPOSED CONCRETE SHEET PILE ALONG KEDAH RIVER
BANK, KEDAH FOR GOVERNMENT OF MALAYSIA

5M

2006

2007

JURUTERA KONSULT MAJU S/B

7

CADANGAN KERJA-KERJA KECEMASAN (AP55) AKIBAT
JALAN RUNTUH, DI KM31, LALUAN C108, JALAN KUALA
MENTIGA-TERAPAI, PEKAN, PAHANG

2M

2009

2009

IMPEX BIO-ENGINEERING S/B

8

PROPOSED INFRASTRUCTURAL WORK FOR TANJUNG
LANGSAT, JOHOR

2M

2009

2009

IMPEX BIO-ENGINEERING S/B

9

GEOGRID WALL FOR LOT 772 & 682, DAERAH HULU
LANGAT, SELANGOR

1M

2006

2009

IMPEX BIO-ENGINEERING S/B

10

PROPOSED DEVELOPMENT OF IRAQI EMBASSY,
OFFICIAL RESIDENCE & CHANCERY IN DIPLOMATIC
ENCLAVE, PRECINCT 15, PUTRAJAYA, MALAYSIA

2M

2009

2009

LANDASAN IMPIAN S/B

11

PROPOSED HOUSING DEVELOPMENT AT SAUJANA
IMPIAN, KAJANG UNTUK TETUAN BANDAR SUBANG
SDN BHD, PHASE 6B & 6D1

3M

2009

2010

BANDAR SUBANG Sdn Bhd

12

FLOOD MITIGATION WORK FOR SG KELANTAN,
MALAYSIA

10 M

2002

2005

MTS FIBROMAT S/B

 
You are here  : Home Project Geotechnical Projects